Snapshot of 6 November 2026
Marina's house, “Beryozovy”
a settlement by the river. Started 2 May 2026, turnkey, 47 weeks. Decisions stay in this browser.
- Now
- Roof and windows
- Week
- 27 of 47
- Handover
- 26 March 2027
- Decisions
- 0 of 2
- Boiler not chosen
2 May 202626 March 2027

The build
26 October 2026 – 17 December 2026
Trusses, roofing, windows and the front door. The shell is then closed.
Range with decisions
11.67 million ₽ – 13.43 million ₽
No extra yet
Waiting on the owner
The roof is underway. Services will not start until the boiler is chosen.
The boiler holds the Services stage. The floor does not change the roof schedule. Press a choice again to clear it.
In the request
- BoilerNot chosen
- Ground-floor floorNot chosen